Informal testing every six months consisting of the following: |
| 1. |
Septic Tank Systems |
|
a. |
Check for sludge accumulation (Greater than 40% requires cleaning) |
| 2. |
Aerobic Treatment Units |
|
a. |
30 minute settleable solids (conducted on the mixed liquor suspended solids) Settleable solids > 65% will require pump out of solids, pump out may be recommended if settleable solids are > 50% |
All Systems (including the above-referenced systems)
A sample of the final effluent from the pump chamber or sample port shall be checked for: |
| 3. |
Odor (a slightly musky odor is normal, septic or rotten egg odors are not normal and indicate that service is required) |
| 4. |
Color (less than 15 units of color is normal) |
| 5. |
pH, (pH between 6.0 and 9.0 is normal) |
Formal Testing Annually consisting of the following: |
| 1. |
All tests and observations listed under informal testing above. |
| 2. |
Collect and analyze a sample of the final effluent for: |
|
a. |
Biological Oxygen Demand (BOD5) |
(test results should be < 30 mg/l) |
|
b. |
Total Suspended Solids (TSS) |
(test results should be < 30 mg/l) |
|
c. |
Fats, Oil & Grease (FOG) |
(test results should be < 5 mg/l) |